The Kamoa Project is a newly discovered, very large, stratiform copper deposit with adjacent prospective exploration areas within the Central African Copperbelt, approximately 25 kilometres west of the town of Kolwezi and about 270 kilometres west of the provincial capital of Lubumbashi. Ivanhoe Mines holds its 95% interest in the Kamoa Project through a subsidiary company, African Minerals Barbados Limited SPRL (AMBL). A 5%, non-dilutable interest in AMBL was transferred to the government of the DRC on September 11, 2012, for no consideration, pursuant to the DRC Mining Code. The company also has offered to sell an additional 15% interest to the DRC on commercial terms to be negotiated.

In January 2013, a new independent mineral resource estimate was prepared for the Kamoa Copper Discovery by AMEC E&C Services of Reno, Nevada. The new estimate ranks Kamoa as Africa's largest high-grade copper discovery and the world's largest undeveloped high-grade copper discovery. As of January 2013, Ivanhoe Mines had discovered Indicated Mineral Resources of 739 million tonnes grading 2.67% copper, containing 43.5 billion pounds of copper, and Inferred Mineral Resources of 227 million tonnes grading 1.96% copper, containing 9.8 billion pounds of copper. A 1% copper cut-off grade and a minimum vertical mining thickness of three metres was applied in each classification.

Kamoa Mineral Resource December 2012

Copper cut-off Tonnage (Mt) Copper Grade Contained Copper (billion lbs)
Indicated Resource
3.00% 224 3.85% 19.0
2.00% 550 3.04% 36.9
1.00% 739 2.67% 43.5
Inferred Resource
3.00% 19 3.40% 1.4
2.00% 93 2.64% 5.4
1.00% 227 1.96% 9.8
Note: Mineral Resources have an effective date of December 10, 2012. Harry M. Parker and Gordon Seibel, both SME Registered Members, are the Qualified Persons responsible for the Mineral Resource estimates. The Mineral Resource estimate was prepared by Mr. Seibel. Mineral Resources are reported using a total copper (Cu) cut-off grade of 1% Cu and a minimum assumed mining thickness of 3 metres. A 1% Cu cut-off grade is typical of analogue deposits in Zambia.

Click here to view the March 2013 Kamoa Technical Report on updated Mineral Resource Estimate

Click here to view the November 2013 Kamoa Preliminary Economic Assessment Technical Report

Two-phased approach to the development of a large mine and smelter

On November 18, 2013, Ivanhoe Mines announced positive findings of an independent, Preliminary Economic Assessment (PEA) of the company's major Kamoa copper discovery.

The PEA reflects a two-phased approach to development of the Kamoa Project. The first phase of mining would target high-grade copper mineralization from shallow, underground resources to yield a high-value concentrate. The second phase would entail a major expansion of the mine and mill and construction of a smelter to produce blister copper.

The PEA contemplates the establishment of a conventional copper mine and concentrator complex at Kamoa with an initial mining rate and concentrator capacity of three million tonnes per year. Initial mill feed would come from the Kansoko Sud mineralized zone and lead into the Centrale area of Kamoa's mineralized zones.

The initial mining rate and concentrate feed capacity of three million tonnes per year would be followed in Year 5 by an additional expansion of eight million tonnes per year in concentrator capacity and the construction of an on-site smelter with a capacity to produce 300,000 tonnes per year of blister copper. In addition, an estimated 1,600 tonnes of sulphuric acid per day would be produced as a by-product in the copper smelting process.The PEA contemplates that the sulphuric acid produced at Kamoa would be sold to copper-oxide mining operations on the Central African Copperbelt that currently purchase acid from Zambia or from overseas.

The production scenario schedules 326 million tonnes to be mined and milled at an average copper grade of 3.0% copper over a 30-year mine life, producing 7.8 million tonnes of payable blister copper (plus 0.5 million tonnes of payable copper in concentrate, in the initial concentrate phase) over the life of the project.

The PEA is preliminary in nature and includes an economic analysis that is based, in part, on Inferred Mineral Resources. Inferred Mineral Resources are considered too speculative geologically to have the economic considerations applied to them that would allow them to be categorized as Mineral Reserves, and there is no certainty that the results will be realized. Mineral Resources do not have demonstrated economic viability and are not Mineral Reserves.

Highlights of the Preliminary Economic Assessment (PEA):
  • A large mine and smelter would be developed using a two-phased approach.
  • A smaller-scale start-up would establish an operating platform to support expansion.
  • Early cash flows would be generated from the sale of high-grade copper concentrate.
  • Low pre-production capital requirement of approximately US$1.4 billion.
  • Steady-state production target of 300,000 tonnes per year of blister copper, which would establish Kamoa as one of the world's largest copper mines, with the highest grade.
  • Cash costs of US$1.18 per pound of copper would rank Kamoa near the bottom of the global cash-cost curve.
  • Pre-tax Net Present Value, at an 8% discount rate, of US$4.3 billion.
  • After-tax Net Present Value, at an 8% discount rate, of US$2.5 billion.
  • Pre-tax internal rate of return of 18.5%; after-tax IRR of 15.2%.


Construction underway of first box cut for planned underground mine


In August 2014, a contract for construction of the box cut for the initial portal to planned decline ramps that will provide underground access to the proposed Kamoa mine was awarded to Lubumbashi-based Mining Company Katanga Sprl (MCK), which has extensive local experience in contract mining and earthworks and has worked on other significant Katanga copper mining projects, including Kinsevere, Kipoi and Kolwezi.

Construction of the box cut is expected take approximately five months, after which development of the first set of twin declines can commence. The declines have been designed to intersect the high-grade copper mineralization in the Kansoko Sud area, approximately 150 metres below surface. Ivanhoe's drilling program in this area has defined a thick, near-surface zone of high-grade copper mineralization, where a recent drill hole, for which assays were received in April 2014, intercepted 15.7 metres (true width) of 7.04% copper, at a 1.5% total copper cut-off.

Progress on pre-feasibility study, with initial mining planned at Kansoko Sud


In line with the phased approach to project development outlined in the 2013 updated Kamoa PEA, the Kamoa pre-feasibility study (PFS) is progressing on the basis of an initial three-million-tonne-per-annum (3Mtpa) mine and concentrator.

The focus in planning the early years of mine production continues to be on the near-surface and high-grade material from the Kansoko Sud area to maximize margins. The 3Mpta mine and concentrator can be split into modules to potentially better match the underground ramp-up and further reduce the pre-production development capital. This will be examined in more detail as part of the pre-feasibility study to provide flexibility to the development of the Kamoa Project.

Mining licence


In August 2012, the government of the DRC granted the mining licences for the Kamoa Project that cover 400 square kilometres. The licences are valid for 30 years and can be renewed for 15 years at a time, until the end of the mine's life.

Agreement signed to upgrade existing hydroelectric power plants


In March 2014, a financing agreement was signed between Ivanhoe and the DRC's national electricity company, La Société Nationale d'Electricité (SNEL). Ivanhoe is working with SNEL to upgrade two existing hydroelectric power plants -- Mwadingusha and Koni -- to recover up to 113 megawatts of capacity to be made available to the national power supply grid. SNEL will provide the Kamoa Project with up to 100 megawatts from the grid, which would be sufficient to operate the initial phase of the Kamoa mine.

A third hydroelectric power plant -- Nzilo 1 -- would follow under the same financing agreement. Nzilo 1 will have a capacity of approximately 108 megawatts upon completion, entitling Kamoa to receive an additional 100 megawatts from the grid. The upgraded technology planned to be applied will increase the original design capacity of these power plants by up to 10%.

A combined total of 200 megawatts from the grid would provide sufficient power for Kamoa's 300,000 tonnes per year smelter and the associated future mine expansions.  
  • Overview
  • Kamoa Project
  • Platreef Project
  • Kipushi Project
  • Exploration Projects
  • Photo Gallery
  • >